Campus Construction Schedule 2007-2009

Parking/Jogging Track/Streets
April - August, 2007
HVAC and Lighting Rehab for FOB, Lecture Hall, and PAC
May - July, 2007
New Buildings
Classroom Building
September, 2007 - November, 2008

Science Building
November, 2007 - April, 2009

Emergency Training Center
January, 2008 - January, 2009
Renovation of:
Student Center
December, 2008 - June, 2009

Student Services Building
July, 2009 - October, 2009
Renovation of Health Careers and Science Building
June, 2009 - December, 2009
HVAC and Lighting Rehab for FA and Maintenance Buildings
May, 2008 - August, 2008
HVAC and Lighting Rehab for AC Building
May, 2009 - August, 2009
Campus Signage
June, 2009 - July, 2009

NB: Construction and renovation schedules are always subject to change. This schedule will be updated as changes occur.